Reading a Contractor's Bid: The Line Items That Hide Risk
Owners usually compare bids by the bottom line. That number is the least informative part of the document. What matters is what is included, what is assumed, and what is deferred.
Start by normalizing scope
Before comparing dollars, build a simple matrix: every major scope on the left, every bidder across the top. Mark included, excluded, or allowance. You will almost always find gaps in site work, utilities, landscaping, appliances, and finish hardware.
A bid that is low because it excludes the driveway is not low.
Allowances are unpriced scope
An allowance is the contractor telling you they do not know the number yet. It is not a discount and it is not a commitment. Watch for:
- Flooring, tile, and countertop allowances set below the level shown in renderings
- Lighting and plumbing fixture allowances with no fixture schedule
- Site work or excavation allowances on a site with no geotech report
- "Utility connection" allowances before the utility has responded
Ask what quantity and quality each allowance assumes. If the answer is vague, the exposure is yours.
Unit prices tell you where the pain will come from
Unit prices for rock excavation, unsuitable soil removal, structural fill, and undercut are the contractor pre-negotiating the most likely overrun. Their presence is a signal, not a red flag. The question is whether the unit rate is reasonable and whether the baseline quantity is realistic.
General conditions and general requirements
General conditions cover supervision, temporary facilities, dumpsters, safety, and site management. They are usually a function of duration. That means a longer schedule is a more expensive project even if nothing else changes.
Look for:
- General conditions expressed as a monthly rate rather than a lump sum
- Whether the rate continues if the schedule extends for owner-caused delay
- Whether supervision is full time or shared across projects
Contingency: whose is it?
Contractor contingency inside a GMP is meant for the contractor''s own risk, not for owner scope changes. Owner contingency is separate and should sit outside the contract sum. Contracts that are silent on this reliably produce arguments later.
Clarify in writing:
- What events can draw on each contingency
- Who approves a draw
- What happens to unspent contingency at closeout
Exclusions and clarifications pages
This is the most important page in most proposals and the least read. Common exclusions worth pricing separately:
- Permit and impact fees
- Testing and special inspections
- Builder''s risk insurance
- Survey and as-built documentation
- Off-hours work, dewatering, temporary power
- Escalation beyond a stated date
Schedule as a pricing document
A bid with no schedule is an incomplete bid. Ask for milestone dates, assumed permit duration, assumed long-lead procurement, and what happens if a long-lead item slips. Switchgear, elevators, windows, and custom millwork drive more schedules than framing does.
A practical comparison checklist
- Same scope matrix across all bidders
- All allowances converted to defined quantity and quality
- General conditions shown as duration-based cost
- Contingency ownership and draw process stated
- Exclusions priced as owner budget lines
- Schedule with permit and procurement assumptions
- Escalation and price validity date
Next step
Run this once and the gap between two bids usually collapses to something small and explainable. That is when you are actually choosing a builder rather than choosing an incomplete document.
