Frustration is not a remedy. The contract is. Work the sequence below before you make demands you can't support.
Start by re-establishing the contract baseline schedule, then document the current status and the specific causes of delay. Determine from the contract whether each cause is excusable, compensable, or contractor-owned, and require a written recovery schedule before releasing further payment on affected work.
| Cause | Typically owned by |
|---|---|
| Late owner decisions or selections | Owner |
| Design errors or omissions requiring rework | Design team / owner |
| Unforeseen subsurface conditions | Depends on contract language |
| Late procurement of long-lead items | Contractor, unless ordered by owner |
| Undermanning or subcontractor default | Contractor |
| Abnormal weather beyond contract allowance | Excusable, generally non-compensable |